Contract amendments can turn an apparently cheap public tender into a considerably more expensive investment. But when is an increase lawful, when does it reflect price adjustments, and when should it raise alarm? In this InfoBuz analysis, we use real data from two Court of Accounts reports published in March 2026, explain Law No. 98/2016, and show the difference between the winning bid, the revised value, work actually completed and money paid. No sweeping accusations and no invented figures presented as facts.
The cheap tender, the expensive bill: where the gap between the bid and final cost begins
A public contract may begin with an attractive bid and, several years later, carry a far higher value. Sometimes the difference stems from indexed costs, an unforeseen circumstance or technically justified additional work. In other cases, missing documentation, a changed scope and unsupported payments become audit issues. A higher price is not automatic proof of fraud, but nor does the simple phrase “materials became more expensive” relieve an institution of the duty to justify it.
For citizens, the central question is whether the amount paid corresponds to an approved and completed result. For journalists, verification starts by reconstructing the contract from the notice to the final payment. This InfoBuz analysis explains the rules and presents specific findings from two Court of Accounts reports published in March 2026, rather than an invented ranking of the most expensive tenders.
Seven different figures in one project: do not confuse them
A project may have a budget estimate, a winning bid, a contract price, a revised contract price, completed-work statements, accepted invoices and actual payments. Its total cost may also include separate procurements for design, supervision, utility relocation and other expenses. Comparing these figures without labels can produce a dramatic but incorrect result.
Example: an authority estimates an investment at 14 million lei, awards the construction work for 10 million, signs amendments bringing it to 11.6 million, but hypothetically accepts and pays only 10.9 million for completed work. It would be false to say that “the final bill was 14 million” merely because that was the estimated value. Financial documents and VAT must be checked separately.
| Figure encountered | Practical meaning | How to verify it |
|---|---|---|
| Estimated procurement value | The authority’s estimate before the tender | Statement of need, procurement documentation, notice |
| Winning bid value | The economic offer declared the winner | Procedure report and bid, subject to access rules |
| Initial contract price | The initial contractual obligation, on the signing date | Contract and financial annexes |
| Revised contract value | The price or ceiling resulting from permitted changes | Amendments, clauses, change register |
| Value of completed and accepted work | Quantities and services actually certified | Work statements, certificates and acceptance records |
| Payments made | Money actually disbursed | Invoices, payment orders, budget execution records |
| Total project cost | May include design, expropriations, utilities, supervision and VAT | Investment budget, separate contracts, consolidated statement |
What Law No. 98/2016 says: changing a contract without a new tender has limits
Article 221 of Law No. 98/2016 sets out the circumstances in which a public procurement contract may be amended without a new procedure, while Article 222 establishes the rule that a new procedure is required outside those cases. Relevant grounds include review clauses provided from the outset, certain necessary additional works or services, unforeseeable circumstances, permitted replacement of the contractor and non-substantial modifications. Law No. 98/2016, official text; Article 221, structured presentation.
There is no rule allowing two parties to sign off on any increase simply because they “agree”. The authority must demonstrate that the change falls under a permitted ground and comply with approval and transparency procedures. The rule concerns contracts within its scope; ANAP separately explains direct procurement, for which Articles 221–222 do not operate in the same way.
| Ground under Article 221 | Conditionally permitted situation | Decisive check |
|---|---|---|
| Point (a) | A clear review or adjustment clause provided initially | The formula, ceiling, conditions and whether it changes the contract’s overall character |
| Point (b) | Additional works, services or goods from the original contractor | Necessity, technical or economic reasons, and the cap conditions |
| Point (c) | Circumstances a diligent authority could not have foreseen | Evidence, no change to the overall character, and statutory limits |
| Point (d) | Replacement of the contractor only in permitted cases | Succession or other special conditions; no evasion of competition |
| Point (e) | Changes that are not substantial | The test of effects on competition, the economic balance and scope |
| Point (f) | Changes below prescribed monetary and percentage thresholds | Aggregation, thresholds, 10%/15% under the statutory conditions, and an unchanged scope |
Price-adjustment clauses set from the outset are different from new work
If the tender documentation contained a clear price-adjustment clause, the calculation may later be applied within its stated limits and conditions. In a long-running project, material or labour costs may change from the time of the bid. The justification concerns the applicable formula, the indices used, eligible quantities and the period for which adjustment is sought.
Additional excavations, a change to the technical design or construction of a new building wing are a different type of change and cannot automatically be justified by inflation alone. ANAP Instruction No. 1/2021 requires an analysis of the nature of the change and the ground relied on. The same instrument says that mechanical application of a clause may be recorded in the appropriate documents without every adjustment necessarily becoming a separate contract amendment.
10%, 15% and 50%: what the thresholds say—and what they do not allow
Article 221(1)(f) provides a special regime for changes below relevant monetary thresholds and also below 10% of the initial price for goods and services or 15% for works, subject to other cumulative conditions. Points (b) and (c) operate under a different regime, in which the 50% limit may arise alongside strict requirements on necessity, technical reasons or unforeseeable circumstances. These percentages describe different legal situations.
They do not mean an authority may raise any tender by 50% at its discretion. Under point (f), where changes are successive, the rule requires an assessment of the cumulative net value of changes made on that ground. For points (b) and (c), also check the rules on successive changes and the ban on using them to avoid a new procedure. ANAP provides clarification on the cap and aggregation of changes.
Does a contract become substantially different if it would have changed the tender result?
This is one of the important tests for a substantial modification: whether the new terms, had they been included from the outset, would have allowed other candidates to be selected, another bid to be chosen or additional operators to take part. The law also considers a change in the economic balance in the contractor’s favour, a considerable extension of scope and certain replacements of the provider.
Not every change in deadline or quantity automatically has that effect. The assessment is specific to the project and the original documents. ANAP Instruction No. 1/2021 develops examples of non-substantial changes and ways to justify the classification. Responsible reporting must present both the change itself and the official analysis explaining why it did not require a new procedure.
Court of Accounts, 2026: three distinct findings in Valea Argovei
Report No. 23132 of 24 March 2026, issued after a compliance audit of Valea Argovei commune in Călărași County, is one source showing why simply counting amendments is insufficient. For different projects, auditors found issues involving missing supporting documents, price adjustments and additional works. Full Court of Accounts report.
The report contains findings and recommendations to recover certain sums; it is an audit document, not a criminal judgment. For this article, we did not obtain updated positions from all parties or evidence that the sums were actually recovered. That is why we present each project and each amount separately, as they appear in the report, without assuming that all amendments were unlawful.
| Case and source | What the official document shows | What does not automatically follow |
|---|---|---|
| Valea Argovei — water/sewerage, report of 24 March 2026 | 17 amendments to Contract 274/2018: 9 concerning value and 8 duration; auditors did not receive sufficient justification to verify the correctness of adjustments | We cannot state that all 17 changes involved unlawful payments |
| Valea Argovei — street paving, Contract 1350/2019 | The Court of Accounts identified a VAT-inclusive addition of 603,788.75 lei for works not properly approved and recommended recovery of the amount | This is not the combined value of all the commune’s contracts |
| Valea Argovei — local roads, Contract 8/2024 | A price-adjustment amendment of 1,590,214.47 lei; the audit separately identified 101,445.49 lei as unjustifiably increased expenditure | The entire 1.59 million lei adjustment was not classified as damage |
| Bârlad — road infrastructure, Contract 49/2022 | 10 amendments; revised contract value of 48,124,351.95 lei excluding VAT, compared with 41,442,554.33 lei initially | The revised contractual ceiling alone is not proof of full payment or illegality |
Valea Argovei: 17 amendments to a water and sewerage project
For design-and-build Contract No. 274/30.08.2018, concerning the wastewater network, treatment plant and water supply, auditors were shown 17 amendments by 30 December 2024: nine changed the value and eight concerned duration. The Court of Accounts recorded that insufficient supporting documents had been provided to establish the justification and necessity of all changes and the correctness of price adjustments.
The report describes several versions of certain site instructions and amendments, with inconsistencies or missing signatures. This is a serious traceability issue, but the number 17 is not, by itself, the value of any loss. For that project, the Court requested verification of the documents and calculation and, should unlawful payments be found, determination and recovery of the corresponding amounts. Source: report, section 5.5.
Valea Argovei: auditors separately flagged 603,788.75 lei in street paving
For the “Street paving in Valea Argovei commune” project, under Contract No. 1350/11.04.2019, the Court of Accounts examined Amendment No. 2 of 10 May 2021, which increased the price by 603,788.75 lei, including VAT. According to the report, the documents provided did not demonstrate that the change fell within permitted grounds, and technical changes and the need for additional quantities had not been properly substantiated.
Auditors also recorded that certain additional works had been included in a payment statement before their approval through the amendment invoked. In its recommendations, the Court sought recording and recovery of the amount, along with a technical analysis of the additions. These are the auditors’ conclusions; InfoBuz did not carry out its own on-site technical assessment and does not state that the sum has already been recovered. Official report, section 5.6.
For a related investigation into responsibility for road-surface interventions, see InfoBuz’s analysis of asphalt dug up after paving and who pays to restore streets. It separately explains why a further intervention does not automatically mean a second payment from the public budget.
A 1.59 million lei adjustment does not mean 1.59 million lei in damage
Another contract in the same commune, No. 8/22.01.2024, for paving roads in the villages of Valea Argovei and Vlădiceasca, had an acceptance-stage value of 10,367,643.89 lei. An amendment on the same day added adjustments of 1,590,214.47 lei, bringing the figure to 11,957,858.36 lei, according to the report. Auditors analysed the calculation of the adjustment.
The Court of Accounts identified 101,445.49 lei in unjustifiably increased expenditure, of which 89,545.49 lei related to applied updates and profit margins and 11,900 lei was an undue difference, and recommended recovery. Therefore, it would be incorrect to present the whole 1.59 million lei as damage. The example shows why the report’s conclusion, rather than merely the rise in contract value, must be read. Official report, section 5.5.
Bârlad, 2026: ten amendments and the revised value of road infrastructure
A second case study comes from Court of Accounts Report No. 20600 of 12 March 2026, concerning the municipality of Bârlad. Contract No. 49/24.05.2022, for modernising transport infrastructure, was awarded through an open tender at 41,442,554.33 lei excluding VAT. The report mentions ten amendments and a revised contract value of 48,124,351.95 lei excluding VAT, following price adjustment.
The increase in contractual value totals 6,681,797.62 lei excluding VAT, or approximately 16.12% of the initial value. However, the auditors also record a value of work calculated without adjustments of 39,685,540.32 lei, 1,757,014.01 lei below the initial value, owing to quantity savings. The revised contract value, the basis of completed work and the amount actually paid must not be confused. Source: Bârlad audit report, March 2026.
Why the Bârlad report cannot be reduced to a “contract inflated by 16%” headline
The Bârlad report examined a broader set of issues, including the legality of payments for a bicycle lane, urban-planning documentation and the performance guarantee. Auditors flagged shortcomings related to updating the guarantee and accepting certain works, among other findings. It does not follow that the entire 16.12% contractual adjustment was declared unlawful.
There are therefore at least three separate questions: did the adjustment have a legal basis? Were completed work quantities certified correctly? Were guarantees and acceptance managed correctly? A sound investigation examines them separately and seeks payment data; it does not use the revised value as sole evidence of an irregularity.
Three different mechanisms that can change the final amount
The first mechanism is price adjustment for certain costs, based on contractual formulas or applicable special legislation. The second is changes in quantities through remeasurement or approved technical changes. The third is the addition of works, services or equipment not initially included, in permitted and justified circumstances.
These mechanisms can operate simultaneously, but should not all be placed in one category labelled “additions”. A price formula may increase while the final quantity of work falls; in that case, the net difference between the initial contract and final delivery does not tell the whole story. ANAP Instruction No. 1/2021, explained in the procurement guide, also addresses recording changes through documents other than amendments.
A 10 million lei contract becomes 11.6 million: a verification example
Imagine a project beginning at 10 million lei excluding VAT. A permitted adjustment formula adds 1.2 million, necessary and approved additional works add 800,000, and omissions of certain quantities reduce the total by 400,000 lei. The resulting value is 11.6 million lei, or +1.6 million and 16%. This is an editorial example, not a real contract.
Mathematics alone cannot determine whether the increase is lawful. The review clause, new work, legal ground, technical documents, applicable cap and actual delivery must all be analysed separately. Arbitrarily deducting an omission from the value of additional works to fit within a legal threshold could produce the wrong conclusion. Each legal ground requires its own calculation method.
| Stage — EXAMPLE ONLY | Change | Cumulative value |
|---|---|---|
| Contract signed | — | 10,000,000 lei excluding VAT |
| Price adjustment under an applicable clause | +1,200,000 lei | 11,200,000 lei |
| Additional works approved on a distinct legal ground | +800,000 lei | 12,000,000 lei |
| Documented omissions of work | −400,000 lei | 11,600,000 lei |
| Net difference from initial contract | +1,600,000 lei | +16% |
What to check about VAT before alleging a cost increase
An amount “including VAT” cannot be compared directly with one “excluding VAT” as though the difference were additional work. The VAT rate and when it applied may also matter for contracts spanning several years. Romania’s VAT regime changed in 2025, so comparing documents from different years requires attention to the VAT-exclusive base and the update method.
For analysis, start with VAT-exclusive amounts where available and comparable, then set out taxes and payments separately. Do not combine an approved estimate including VAT with an award price excluding VAT. In Bârlad’s case, the report explicitly gives both the initial and revised values excluding VAT, allowing the percentage to be calculated without this error.
Why the “lowest price” does not automatically mean the best investment
An authority may use award criteria permitted by law, including the lowest price under the applicable conditions, but the quality of the documentation and the bidder’s capacity to deliver remain essential. A very low bid may be legitimate, for example because of operational efficiency, favourable material sourcing or better technology. It may nevertheless warrant scrutiny of the price’s sustainability and the technical assumptions behind it.
Do not assume that every cheaply won tender is a tactic for subsequently increasing the contract. Such a mechanism would need to be proven through specific documents and circumstances. The InfoBuz article on the seven documents in a public tender explains how to scrutinise bids and awards; this analysis follows the trail after signature.
Technical-design quality: the unseen cause of many changes
An insufficiently investigated project may later reveal unsuitable ground, unmapped pipes, unbuildable solutions or quantities different from those estimated. Some discoveries may genuinely be unforeseeable; others could have been prevented by adequate investigations at the preparation stage. The distinction matters in justifying a contract change and assessing responsibility.
A document called a “site instruction” must be signed and checked under applicable rules and technical conditions, not simply attached to an invoice. In the Valea Argovei audit, the Court of Accounts flagged problems precisely with multiple versions of some instructions and missing documents for certain additional works. A site finding should state what was discovered and why the initial solution is no longer appropriate.
How amendments can be used to extend a construction project
Not all amendments change the price. Some extend the completion period for contractual, funding, access or technical reasons. In Valea Argovei, eight of the 17 changes to the water-and-sewerage contract examined concerned duration. This must be tracked separately from the nine value changes.
A delay can create indirect costs, but it should not automatically be converted into an extra cost identical to the value of the extension months. What matters is who is responsible for the delay, whether penalties apply, which equipment and staff were retained, whether funding remained valid and whether new expenditure was actually accepted.
The change register: the document to follow, not only amendments
ANAP explains that authorities must prepare and update a contract change register under Instruction No. 1/2021. The register tracks changes, including how review clauses are applied and their financial effect. Certain adjustments or remeasurements may be documented through work statements, invoices or other contractually accepted instruments, not exclusively through amendments.
In answers published in the procurement guide, ANAP says the register is not public by default, but access to it may be requested under legislation on information of public interest. Do not confuse it with the procurement file before award: it is primarily a contract-implementation tool. Source: ANAP, case 1108 and related clarifications.
SEAP and TED: where contracts and modification notices can be found
Romania’s public procurement system makes it possible to identify procedures and relevant notices. For contracts subject to European rules, TED/eForms separately describes notices of a contract modification during performance, where required under the applicable conditions. A modification notice may state what changed from the original award.
But a public modification notice is not the same as a consolidated list of all invoices and payments. It may be necessary to consult the authority’s portal, the executed budget or request further documents. For a long-running project, search by procedure number, contract number, institution, subject and procurement identification code, not only by a generic title such as “street modernisation”.
The order for reconstructing a contract timeline
Start with the original documentation and the procedure report. Record the award date, the successful bid, the signing date and the date of the notice to proceed. Add every modification document with its date, invoked legal ground, gross or net value, effect on the deadline and the people who approved the change. Mark the final acceptance date and the last available payment document.
A proper timeline helps identify work that may have been paid before approval, documents issued after the deadline, or cumulative values that do not match. It does not by itself prove illegality, because some review clauses operate under the contractual mechanism. Comparison must be made against the documents and regime applicable on each date.
When a contract falls but the project still costs more
A construction contract can contain omitted quantities while total investment costs increase for other reasons: additional design, utility relocations, price adjustments, financing or separately awarded work. Therefore, a saving on one contract is not automatically a saving on the entire project.
The Bârlad example is instructive: the audit document presents both the increase in contract price through adjustment and a value of work, before adjustment, lower than the contract base. Without these two layers of calculation, a headline can mislead. Total cost requires adding only comparable values and avoiding double counting costs already included in the contract.
Five warning signs in a public contract with many changes
One sign is repeated additions of similar work without a technical explanation. Another is reliance on unforeseeability for information that could have been known through initial studies. A third arises when work statements include quantities not found in approvals or technical documentation. A fourth is the absence of a change register or the existence of contradictory versions. A fifth is incomplete acceptance associated with insufficiently managed payments or guarantees.
All are indicators to investigate, not verdicts. A press investigation should seek explanations from the institution and contractor, and audit-authority findings must be explicitly attributed. If apparent irregularities emerge, separate confirmed documents, unanswered questions and conclusions that an audit or court can establish.
How a real quality change can be hidden without a major price increase
Sometimes the final price remains close to the initial one, while actual performance may be less extensive or poorer. For example, a specified material class could be replaced with an inferior one, quantities reduced or some installations omitted, while the total value does not fall to the same degree. Such an imbalance may be relevant to the substantial-modification test.
Do not state that this happened in a specific project without technical and financial evidence. It explains why analysis focused solely on “how much did the contract rise?” can overlook quality. The technical design, specifications, approvals, quality checks and acceptance records are needed.
Performance guarantee and acceptance: who protects the investment after payment?
A performance guarantee can provide a contractual protection mechanism under the law, while acceptance records the inspection of the work. If the value or duration of the contract changes, guarantee documents may need updating in accordance with applicable obligations. Otherwise, an institution may be exposed precisely when remedial work is needed.
The Bârlad audit report flagged shortcomings concerning updates to the guarantee’s validity and acceptance of part of the work, matters distinct from the adjustment value. For readers, the essential question is whether the work was delivered, inspected and covered by guarantees, not merely whether every document bears the necessary signatures.
Public cost can rise without the town hall making a second payment
A project may have European, national or local financing, each with distinct eligibility rules. If certain expenditure becomes ineligible or funding ends before completion, the share borne by the local budget may change even where the value of some work is technically justified. Thus, who finances it is not the same question as what the contract costs.
The review should include the funding agreement, amendments, council decisions and budget execution. In its Bârlad report, the Court of Accounts described funding extensions and local obligations for certain later expenditure. Do not automatically extrapolate this rule to every European project, however: each programme and contract may have different terms.
Eight documents for following the money after a tender award
For a reproducible review, start with the notice and documentation, the procedure report, the accepted bid, the contract and annexes, the change register, amendments and justifications, work statements and certificates, invoices and payments, followed by acceptance records and guarantees. Some are published; others can be requested through legal mechanisms, within applicable limits.
An institution that sends only a table showing the initial and final amounts has not answered the question of justification. Ask for the legal ground for every change and the documents on which it relied. For the initiation and award stage, see InfoBuz’s guide Who wins a multimillion-leu tender?. Here we extend the review to performance and payments.
| Document to request | Why it matters | Question it answers |
|---|---|---|
| Procurement notice and documentation | Original assumptions and scope | What was promised before bidding? |
| Procedure report and bid price | Criteria, competition and winner | How was the initial price reached? |
| Contract and financial annexes | Price, quantities, formulas and deadlines | What was agreed at signature? |
| Contract change register | Timeline and grounds for changes | How many changes were made, and why? |
| Amendments / instructions / orders | Changes approved in permitted forms | Who approved the new obligation? |
| Supporting analyses and site instructions | Need, calculations and alternatives | What specifically changed in the work? |
| Work statements and payment certificates | Quantities delivered and validated | What was completed? |
| Invoices, payments, acceptance records and guarantees | Final cost and verified quality | What was paid and what was delivered? |
How to request the change register and justifications under Law No. 544
You can ask the contracting authority, through a request for information of public interest, for a copy of the change register and supporting documents for a contract identified by number, date and subject. State the time period and separately request records of price, quantity and deadline changes. Also request, to the extent legally available, consolidated work statements and payments made.
Law No. 544/2001 sets rules on responses, access and statutory exemptions. If documents contain protected information, the authority may consider partial disclosure under the law; there is no guarantee that every record will be published in full. On the difference between petition deadlines and access to information, see InfoBuz’s guide to Law No. 544 and petitions.
A document-request template ready to adapt
“Hello. Under Law No. 544/2001, please provide, for public procurement contract No. [number]/[date], concerning [subject], concluded by [institution], the following information and documents insofar as they may lawfully be disclosed: the initial price excluding VAT; the change register; amendments and supporting documents; the updated contract value; the value of accepted works; invoices and the total of actual payments, separately from committed amounts; and the date and conditions of acceptance. Please also state where this information is published, if an accessible electronic register already exists.”
This template does not require allegations of fraud and can be sent through the institution’s official channels. Specify separately whether you are interested in physical progress, payments up to a particular date or the full project cost. Do not seek unjustified publication of personal data, and do not assume that a document’s absence from a website proves it does not exist in the records.
An InfoBuz editorial protocol for correctly comparing ten contracts
For a comparative investigation, we propose selecting ten public contracts using written criteria set before data collection: the same category of works, a similar period, comparable initial value and available documents. For each, record the VAT-exclusive contract price, every change and its ground, the certified sum, payments, acceptance and duration. Then have a sample of documents checked by a technically or legally qualified person.
This is a proposed editorial protocol, not a field study already conducted by InfoBuz. The audit examples cited in this article are cases published by the Court of Accounts, not a representative sample of all tenders in Romania. If research is expanded, data from authorities must be retained with its source and extraction date, and the entities concerned must be asked for responses before accusatory conclusions are published.
Which indicators show whether an authority manages contracts well?
A set of indicators would include the percentage of contracts with revised values, the types of legal grounds used, the net value of changes per contract, delay against the initial deadline, the share of work accepted without reservations, actual payments and the value of remedies carried out under guarantee. The data must be reported for the same procurement category and the same stage of performance.
Do not compare a completed investment with one barely started without marking the difference. A complex infrastructure contract may carry different risks from the purchase of standard goods. There is no percentage of amendments above which corruption can automatically be inferred; a high number may justify further audit, not a criminal conclusion.
Frequently asked questions about tenders and contract amendments
Can a town hall lawfully increase a contract after a tender? Yes, in applicable cases and within the relevant limits. Does 50% mean it can freely add half the price? No; there are cumulative conditions and bans on evading competition. Must every adjustment be a contract amendment? Not in all cases, where properly documented contractual mechanisms apply. Does SEAP automatically show all invoices? No.
How can I verify an increase? Compare the original documents, the grounds for change, registers, calculations and payments. What does a Court of Accounts finding mean? It is an audit result, not automatically a criminal judgment. Can I request the documents? You may request information and documents under Law No. 544, within its limits and conditions. Is the updated price the amount already paid? Not necessarily.
Official sources, audit documents and limits of this investigation
Legal basis: Law No. 98/2016, Articles 221–222, ANAP — guidance and explanations on Instruction No. 1/2021, ANAP — changes, thresholds and aggregation, ANAP — direct procurement, and TED — notice types and contract modifications.
Primary documentation: Court of Accounts, Report No. 23132/24.03.2026, Valea Argovei administrative-territorial unit; Court of Accounts, Report No. 20600/12.03.2026, Municipality of Bârlad administrative-territorial unit. The analysis was written and reviewed on 23 November 2026. Amounts in the mathematical examples are hypothetical. We did not obtain individual contracts and payments directly from all parties, did not verify investment delivery on site, do not hold a complete national database of contract amendments, and do not claim that an audit establishes an individual’s criminal liability. The distinction between findings, recommendations and recovered payments is maintained throughout this article.











Discuția cititorilor
Ai o opinie sau o întrebare despre acest articol? Spune-ne ce crezi.
Fii primul care deschide discuția.
Te rugăm să păstrezi un limbaj civilizat și să discuți la subiect. Comentariile spam sunt filtrate automat.